Stockman Project Scoping Study Confirms Project Economics

Monday, 06 December 2010 09:00

  • Stockman Project Scoping Study completed
  • 7-8 year project life with significant potential upside
  • Annual free cash flow of ~$70M per annum over first 5 years and ~$50M per annum for following years
  • Project development CAPEX of circa $185 million
  • Native Title and Mining License granted
  • Full Definitive Feasibility Study now commenced  
     
 

JML Constitution

Monday, 06 December 2010 09:00

Read more: JML Constitution

 

AGM Presentation November 2010

Friday, 26 November 2010 09:00

  • Jaguar Mine - lowest cost quartile
  • Jaguar Project +8 year reserve
  • Jaguar Project upgrade
  • Strong Project pipeline

 


Read More

   

Results of Annual General Meeting

Friday, 26 November 2010 09:00

  • Results of Annual Meeting of Shareholders 

Read More

 

Bentley Resource Upgrade

Tuesday, 23 November 2010 09:00

  • 30% increase in Bentley Resource
  • Bentley total 3.05Mt @ 2.0% Cu, 9.8% Zn, 0.6% Pb, 139 g/t Ag, 0.7 g/t Au 

 